Project Spotlight: Insulation for a New $150 Million Gas Processing Plant

When the request went out to fill the specs for insulation on the first of three plants in a new $150 million Blue Racer Midstream gas processing facility, Industrial Insulation Group answered the call. The plans required high temperature insulation with a high compressive strength that could stand up to foot traffic and the elements. Blue Racer was also looking for a flexible solution to wrap two 500-foot propane tanks that filled a somewhat confined space.

Upon completion, the plant would process 200 million cubic feet of gas per day derived from the highly-productive Utica Shale fields in Eastern Ohio. The project was also on a fast-track schedule, so the insulation had to be not only perfect for the job, but also readily available. This Project Spotlight summarizes how Industrial Insulation Group rose to the challenge.